Village of Avon WWTP
Over the years, MRB Group has designed
improvements and administered construction for a number of projects at the
Village sewage treatment plant. Upgrades and improvements to various components
of the facility have been done. Representative projects that have been
completed over the past several years include:
- Trickling filter improvements including a cover (shown).
- Anaerobic digester improvements including a pump system.
- Clarifier rehabilitation.
- Pump replacements and improvements.
- Digester cleaning, sludge dewatering, and disposal for 60’ tanks.
One especially innovative use of technology that was implemented on this
project was the use of reed beds. By planting phragmite reed beds in the
existing sludge drying beds (shown), the drying process was improved and
the sludge hauling costs were significantly minimized. Overall, this resulted in
a minimal capital expense to the Village.
These improvements have all been reviewed and approved by the New York State
DEC.
|